SUBWAY fast food store in Beijing railway station


Kiosk for "SUBWAY".

Location - Beijing Railway Station, Shanghai

Time Limits: Design service - 14 days. Prefabrication + preparation + installation - 25 days

1. Design Service Phase:

To Design for such brands like "SUBWAY" is a challenge. Key point is to balancing between brand design standards and create right emotion for customers. Here big influence played - non standard location, Brand demands, Landlord demands, neighboring and ets.

2. Prefabrication and Construction preparation:

Prefabrication start parallelly with construction and engineering preparation. TIME is twise shorter than in regular construction. Minimum Noice and NO SMELL!

3. Installation.

#Subway #HYBRIDPREFABRICATION